Archi-Civilarchi-civil.com
Prestressed Concrete · ÖNG-02  |  Confidence: A
Figures are produced by engine/prestress.js and pinned in tests/prestress.test.js.

Home / Articles / Prestressed Concrete ÖNG-02

Where Can the Cable Go?

ÖNG-01 showed that a constant eccentricity is hostage to the support and wastes the section at midspan. So what is the right layout? The answer comes from four inequalities at every section — and in this case the zone turns out to be empty at midspan.

Confidence: A Engine: engine/prestress.js Tests: tests/prestress.test.js — 46/46 Prerequisite: ÖNG-01 Reading: ~15 min Last verified: 2026-09-10 Türkçe: bu yazının Türkçesi
A note on codes for the international reader The cable zone derivation here is universal: it follows from the fibre stress relations and holds under any national code. Only the four allowable stress values come from a code, and in the worked example they are Turkish values. Our engine stores no code value and takes them as inputs — so the same calculation can be run with ACI, Eurocode or any other set.

1. The question left open

At the end of ÖNG-01 we saw this: with a constant eccentricity the governing section is the support, and the limit the support imposes leaves the section under-used at midspan. In the corrected design the midspan utilisations came out at 0.21 and 0.64.

The natural question follows: if the cable need not run straight, where may it sit at each section?

2. Two states, four conditions

A prestressed beam is checked at two separate moments, and the two push in opposite directions:

Two fibres are checked in each state; four conditions in total:

TRANSFER (Pi, Mmin)
top fibre tension   Pi/A − Pie/W₁ + Mmin/W₁ ≥ −fct,i
bottom fibre compression   Pi/A + Pie/W₂ − Mmin/W₂ ≤  fcc,i

SERVICE (Pe, Mmax)
top fibre compression   Pe/A − Pee/W₁ + Mmax/W₁ ≤  fcc,s
bottom fibre tension   Pe/A + Pee/W₂ − Mmax/W₂ ≥ −fct,s Solved for e, the transfer conditions give an UPPER limit and the service conditions a LOWER limit. The cable zone lies between them.

3. Why transfer gives an upper and service a lower limit

This symmetry is not accidental but physically necessary.

At transfer there is no load to balance the prestress. As the eccentricity grows, the prestress moment grows and drives the top fibre into tension and the bottom into excessive compression. So a larger e makes things worse → an upper limit.

In service the external moment drives the bottom fibre into tension, and what balances it is the prestress moment. If the eccentricity is too small, the balance fails. So a smaller e makes things worse → a lower limit.

Consequence The cable zone is the interval between two opposing demands. The wider it is, the more comfortable the design. Narrowing signals a section under strain; closing signals a section that is not sufficient.

4. At the support: the same number as ÖNG-01

At the support Mmin = Mmax = 0. Computing the zone:

ConditionLimitType
computing…
Transfer conditions set the upper limit, service conditions the lower.
Internal consistencycomputing…

This means two separate functions of the engine — one computing the constant-eccentricity limit, the other the cable zone — arrive at the same number by independent derivations. It is kept as a separate case in the test suite.

5. At midspan: the zone is empty

At midspan the moments enter: the self-weight moment M₀ at transfer, and the total moment in service.

ConditionLimitType
computing…
The lower limit comes out above the upper limit.
Findingcomputing…

One detail deserves attention: the upper limit found here is precisely the 46.3 cm discussed in ÖNG-01. In the original solution that value was found as "the eccentricity optimised for midspan", and it was correct — but only for the transfer condition. The service condition was never checked, and at this section it cannot be satisfied.

6. What does an empty zone mean?

Not a calculation error An empty zone is not a software or arithmetic fault. Its meaning is exact: at that section no eccentricity can satisfy the transfer and service conditions together. Move the cable up and the bottom fibre cracks in service; move it down and the top fibre cracks at transfer. There is no place in between.

What can be done is limited, and none of it concerns cable placement:

7. An independent cross-check

Now the interesting part. We can compute the section modulus that would bring the zone to exactly zero width — that is, "how large would the section have to be for the zone to be only just closing?"

QuantityValue
computing…
Derived holding the section area constant and varying only the section modulus.
Cross-checkcomputing…

The two routes are entirely independent. A direct section check finds the required modulus in one step from the stress limits. The cable zone approach sets up four inequalities, writes the zone width and sets it to zero. That they land on the same number is evidence that both are correctly constructed.

8. Behaviour along the span

As you move along the beam and the moment grows, how does the zone change?

Position (x/L)MserviceeminemaxWidth
computing…
A parabolic moment distribution is assumed for a simply supported beam.

Both limits rise with the moment — and that is the direct answer to why tendons are laid out parabolically: the cable must follow the moment diagram, because the permissible zone follows it too.

But the lower limit rises faster than the upper one, because the service moment is larger than the transfer moment and the service force smaller than the transfer force. So the zone narrows towards midspan, and at this section it closes.

9. What the zone does not tell you

The physical limit is separate The cable zone follows from stress conditions only. Whether the cable physically fits inside the section — cover, duct diameter, spacing between ducts, the anchorage zone — is an entirely separate check and is not part of this calculation. A zone that is valid in stress terms may fall outside the section.

In this case the zone is empty anyway; but even if it were not, whether the eccentricity found is less than half the section depth would have to be checked separately. In another problem mentioned in ÖNG-01 the required eccentricity came to 89.74 cm while the section geometry allowed at most 62.5 cm — physically impossible. The stress calculation does not say so on its own.

10. What to do in practice

  1. Plot the zone along the beam, not at one section. An eccentricity satisfied at one section may fail at another — that was the whole subject of ÖNG-01.
  2. Check both states together. Looking only at transfer produces exactly the 46.3 cm error in that case.
  3. Treat a narrowing zone as a warning. A width approaching zero means construction tolerances alone could break the design.
  4. If the zone is empty, stop working on cable placement. The problem is in the section or in the force, not in where the cable sits.
  5. Check the physical layout separately. The stress zone may not fit inside the section.
  6. Verify by two independent routes. A direct section check and the cable zone must agree; if they do not, one of them is wrong.

11. Test yourself

  1. Why do transfer conditions give an upper limit for e and service conditions a lower one?
  2. Why does the upper limit of the cable zone at the support coincide with the constant-eccentricity limit?
  3. Which four interventions can close an empty zone? Which of them is double-edged?
  4. Why are tendons laid out parabolically? Answer in terms of the zone.
  5. Why does the zone narrow towards midspan? Which two effects produce that together?
  6. Why might an eccentricity that is valid in stress terms still be unusable?
  7. What does it mean that two independent routes give the same required section modulus? What if they had not?

References

  1. Prestressed concrete stress conditions and the cable zone (limiting zone) concept — classical structural engineering results, independent of any national code.
  2. Allowable stress values in the worked example are Turkish code values; the engine stores no code value and takes them as inputs.
  3. The problem belongs to a graduate course in prestressed concrete; the exposition, derivations and all figures here are our own.

All figures in this article are produced by engine/prestress.js and separately pinned in tests/prestress.test.js (46/46). Two internal consistency checks are kept as separate test cases: that the zone's upper limit at the support equals the ÖNG-01 constant-eccentricity limit, and that the section modulus closing the zone agrees with the direct section check.

Open the cable zone tool → ← ÖNG-01: constant eccentricity Türkçe okuyun →
archi-civil.com — Where Can the Cable Go? · ÖNG-02 · Confidence A · Printed:
An empty zone is not a calculation error but a measure of section inadequacy.