Crew Sizing Calculator
Crew size from a target duration, or duration from a crew — entered either as total man-hours or as quantity × productivity. Productivity is a local, method-dependent figure and must be supplied; it is never assumed.
Inputs
Results
Required crew size—
Total work content—
Man-days—
Actual finish with the rounded crew—
Method
Modelduration = man-hours / (crew × hours per day). Linear, and that is its limitation: output stops scaling with crew size once the work face is congested, so a large crew number is an upper bound rather than a schedule.
RoundingA crew is a whole number of people, so the requirement is rounded up — which means the work finishes early, not on the target date. The actual finish is reported so the slack is visible instead of hidden.
ProductivityMan-hours per unit is a required input, not a stored table. Published unit-price analyses revise these figures annually and they vary with method, access and season; this tool will not substitute a typical value for yours.
ConfidenceLevel A for the arithmetic. No allowance is made for weather, learning curve or crew interference.
Planning estimate only. Does not account for crew coordination limits, site access/space constraints, weather, or productivity curves for very large or very small crews.